Mangahewa - MEC
List all projects
Application/s: New Foundations
Location: Mangahewa
Main Contractor: Worley Parsons
Cost: $500k
Having worked on previous stages with both Worley Parsons and Toddy Energy – Piletech were engaged in an Early Contractor Involvement to help understand the ground risk, and complete the most efficient design.
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10

However with a live high pressure methane line running adjacent to the new construction site – there was significant potential for multiple fatalities and lost revenue that would run into the multi-millions!  Needless to say our client required a piling contractor with impeccable safety standards.

Piletech were not only able implement rigorous and robust safety procedures but also adapted the standard working methodologies to effectively eliminate or significantly isolate large portions of construction risk.

The construction works (91 piles to approx 9-12m in depth) were completed within programme (7 days onsite) and on budget.

Piletech then delivered on Health and Safety (0 LTI’s, 0 MTI, 0 First Aid), Environmental (0 Env Incidents), and Quality (no defects).

The result was a happy customer who is already lining Piletech up for the next section of works.